Wirechief, the full simulation.
An emerging contractor building open-access fibre networks, juggling hundreds of weekly underground utility location requests. The case followed on this page, the start of drilling on Glenwood Avenue, with a locate to renew in Garner the same week.
An emerging contractor building open-access fibre networks, juggling hundreds of weekly underground utility location requests.
Not a shovel in the ground without a valid utility locate and permit.
- Wirechief was founded by a former cable operator construction superintendent and a network engineer. Based in Raleigh, the business deploys fibre infrastructure across mid-sized North Carolina cities, opening networks to multiple service providers. It employs twenty-six staff and directs subcontracted civil excavation crews.
- Before breaking ground, excavation crews must submit a locate request to the state 811 centre at least three full business days in advance. Underground asset owners then mark their buried lines, with tickets remaining valid for 28 calendar days.
- Across the United States in 2025, 221,717 incidents of damage to underground facilities were reported, with telecoms and cable lines accounting for 51%. At Wirechief, locate tickets and right-of-way permits were tracked across disparate spreadsheets, leading crews occasionally to dig under expired tickets.
- An agent drafts locate tickets directly from crew scheduling data three full working days before excavation begins, confirming that the municipal work permit is already secured. The construction supervisor officially submits each ticket.
- It monitors responses from all utility operators and alerts the supervisor if any markings are missing or if a ticket is approaching expiration.
What remains with the teams
The construction supervisor holds sole discretion to clear crews for digging after visually inspecting ground markings on site. Only utility asset owners mark their lines, and the agent never authorises excavation work.
- Worksites started with valid utility locates
- Tickets expired during active excavation
- Utility strikes on existing networks
- Time spent managing 811 locate tickets
Right-of-way permits
The agent compiles permit application documents submitted to local authorities and tracks their responses.
The project manager signs each application.
As-built documentation
At the end of each section, the agent compiles team surveys to produce the as-built network plan.
The engineer approves each plan before transmission.
Damage reporting
When a team damages a network, the agent prepares the report with photos and the locate request number.
The safety manager decides on each report and the actions to be taken on the workstream.
Customer drops and connections
Once the street is finished, the agent schedules connection appointments with households that have signed up.
The technician confirms the cable route on site.
the start of drilling on Glenwood Avenue, with a locate to renew in Garner the same week
A drilling workstream starting on Monday, before and after.
- The schedule
- Crew dates change, and locate requests lag behind.
- The agent prepares requests three full business days before each start.
- First workstream
- The permit
- A crew arrives on a section whose permit has not yet been granted.
- The agent verifies the permit before preparing the locate request.
- First workstream
- The responses
- No one knows which utility operators have already marked their lines.
- The agent tracks each response and alerts the site manager when a marking is missing.
- First workstream
- Expiry
- A request expires mid-job, and the crew carries on unaware.
- The agent sends a renewal reminder three business days before expiry.
- First workstream
- Street works permit
- Permit applications are assembled manually for each municipality.
- The agent gathers the documents and tracks responses.
- Workstream 2
- The as-built plan
- The plan of the built network arrives weeks after the section is completed.
- The agent compiles crew survey data at the end of each section.
- Workstream 3
- Read the schedule
- It reads the crew schedule daily and identifies upcoming starts.
- Check the permit
- It verifies that the street works permit has been obtained for each section.
- Prepare the request
- It prepares the locate request with the route and dates.
- The site manager submits each request.
- Track responses
- It tracks the response from each network operator.
- Alert
- It alerts the site manager when a marking is missing.
- The site manager decides whether or not to dispatch the crew.
- Renew
- It prepares the renewal of requests for ongoing works three business days before expiry.
- The site manager submits each renewal.
- Archive
- It keeps each request with its responses and photos of the markings.
- Report
- Each week, it prepares an update on upcoming jobs and pending requests.
- The crew schedule
- Sections and start dates.
- Read-only
- The 811 centre portal
- The status of each request and responses from operators.
- Read-only
- The permit records
- Street works permits granted by the cities.
- Read-only
- The locate tracking table
- Ongoing requests and responses from operators.
- Write
- The site messaging system
- Alerts sent to site managers.
- Alert dispatch
- The founders
- Define the agent's rules with us and choose the next workstream.
- The site manager
- Submits requests and decides alone whether to dispatch a crew.
- The excavation crews
- Verify markings on site before digging.
- The safety manager
- Decides on measures following each incident.
- The FDE
- Leads the engagement and writes the agent's rules with the team. He is accountable for each agent.
- Locates agent
- Prepares requests and tracks responses.
- Permits agent
- Gathers permit documents and follows up with cities.
- Plans agent
- Assembles survey data into as-built plans.
- Control agent
- Compares prepared requests against actual start dates weekly and flags any recurring error to the FDE.
- A crew digs without complete markings.
- The agent flags each missing marking, and the site manager decides alone whether to dispatch the crew after on-site verification.
- A request expires mid-job.
- The agent sends a reminder for each renewal three business days before expiry.
- The agent prepares an incorrect request.
- The agent has read-only access to the 811 centre portal, and the site manager reviews and submits each request.
- Damage goes unreported.
- Each incident reported by a crew triggers the preparation of the report, and the safety manager decides.
- Customer data leaks.
- Household addresses remain in Wirechief's system, and every access is logged.
- We measure the baseline over one month, such as starts with a valid locate, expired requests, reported damage and time spent on requests. The site manager writes the alert rules with us.
- The agent prepares requests in parallel with the team for two weeks, and we compare its tracking against spreadsheets.
- Each morning, the site manager works from the briefing prepared by the agent.
- We compare against the baseline and choose the next workstream with the founders.
- Jobs started with a valid locate
- Share of starts with a valid request and all markings received.
- Requests expired mid-job
- Requests that expired before work was completed.
- Damage caused to existing networks
- Reported damage, compared against the baseline month.
- Time spent on locate requests
- Time logged by the team, compared against the baseline month.
North Carolina 811, Frequently Asked Questions